Karridale Construction has completed projects all over Australia. These range from small brownfield projects through to large scale minerals processing facilities.
A selection of completed projects is outlined below.
BUNBURY PORT RADIAL SHIP LOADER |
Client: |
Krupp Engineering
|
 |
Location: |
Bunbury, Western Australia
|
Project Scope: |
Karridale Construction was responsible for the installation of a radial Shiploader. All sections were transported from Perth to site where each section was lifted into position sitting on 6 metre favco towers, these were then aligned and site welded, all lifts were completed by a 200 tonne lattice jib crane.
|
MINARA RESOURCES NICKEL HEAP LEACH |
Client: |
Minara Resources
|
 |
Location: |
Murrin Murrin, Australia
|
Project Scope: |
Karridale was responsible for the Agglomerator, Stacker and overland conveyor installation. In addition to this, Karridale assisted with the commissioning and in the developmental heap nickel leach project at the existing Murrin Murrin site, including associated infrastructure and commissioning.
|
WHIM CREEK COPPER PROJECT |
Client: |
Straits Resources
|
 |
Location: |
Whim Creek, Australia
|
Project Scope: |
Involved in the Installation of a 500 tonne per hr crushing and stacking circuit. On the successful completion of this, Karridale was requested to install the fuel farm, acid farm, and complete the electrowinning and solvent extraction buildings. |
PENRICE SODA PRODUCTS |
Client: |
QMS Engineering
|
Location: |
Angaston, South Australia
|
Project Scope: |
Installation and commissioning of a 400 tonne per hour crushing and stacking circuit for various lime stone products. |
ARGYLE DIAMONDS |
Client: |
Macmahon for Rio Tinto
|
Location: |
Australia
|
Project Scope: |
Dismantling and salvaging of two alluvial mobile screening plants consisting of apron feeder, bivutec screens and conveyors. |
ADELAIDE TO DARWIN RAIL BALLAST & AGGREGATE CRUSHING PLANTS |
Client: |
Roche Mining
|
Location: |
Western Australia/Northern Territory
|
Project Scope: |
Dismantle 500 tonne per hour crushing plant in Tarmoola, Leonora, Western Australia.
Load – unload Tennant Creek, Northern Territory re-erect refurbish on site.
Modify crushing plant and install additional conveyor systems and stacker to client specification
Install new 150 tonne/hour aggregate plant through to commissioning of both plants.
Installation of 500 tonne/hour crushing plant Katherine, Northern Territory.
Extending and modifying conveyor systems for new plant layout.
Installation of steel panelled Rom walls also carried out on these projects |
Nifty |
Client: |
Macmahon Australia
|
Location: |
Nifty, Australia
|
Project Scope: |
Maintenance of all crushing equipment and agglomerator system and installation of overland conveying systems.
Planning and relocation of grasshopper conveyor systems for leach pad stacking. |
NYNGEN, NEW SOUTH WALES – NIFTY WESTERN AUSTRALIA |
Client: |
Macmahon Australia
|
Location: |
New South Wales/Western Australia
|
Project Scope: |
Dismantle hard rock crushing plant, along with associated overland conveyors, conveyor systems, and stacker.
Load – unload re-erect Nifty Mine.
Modify crushing plant conveyor systems and overland conveyors to client’s specifications. |
HAMMERSLEY IRON |
Client: |
Krupp Australia
|
Location: |
Dampier, Australia
|
Project Scope: |
Installation through to commissioning of a 1700 tonne per hour under slung bucket wheel reclaimer. |
ALCOA |
Client: |
Krupp Australia
|
Location: |
Pinjarra, Australia
|
Project Scope: |
Installation and commissioning of a 1500 tonne/hour reclaimer. |
WESFARMERS COAL |
Client: |
Malco Engineering
|
Location: |
Collie, Australia
|
Project Scope: |
Installation and commissioning of 1500 tonne per hour stacker, and a 1200 tonne per hour reclaimer. |
WESTERN MINING COMPANY |
Client: |
Howden Sirocco
|
Location: |
Leinster, Australia
|
Project Scope: |
Installation of two large centrifugal fans associated steel work, and ducting. |
GREENBUSHES - MEEKATHARRA |
Client: |
K.C. Dodd for St Barbara Mines
|
Location: |
Australia
|
Project Scope: |
Dismantle hard rock crushing plant at Greenbushes.
Load – unload, re-erect in Meekatharra including additional conveyors, and stock pile steel work through to commissioning. |
NORDBERG (AUSTRALIA) WORKSHOP |
Client: |
Nordberg
|
Location: |
Australia
|
Project Scope: |
Assembling and testing of circular and linear motion vibrating screens, grizzlies, and plate feeders. |
FERRO GULLY |
Client: |
Nordberg Australia for Eltins
|
Location: |
Mt Newman, Australia
|
Project Scope: |
Install crushing, screening and conveying duct control equipment sample plant for a 800 tonne per hour ore through to commissioning. |
|